NEA terminates Dhalkebar contract

Nepal Electricity Authority (NEA) has terminated the contract of Dhalkebar substation as the Chinese contractor had intentionally delayed the works of the project.
The project is critical for Nepal-India electricity trade, and the termination of contract could lead to load shedding. But the Central China Power Grid International Economic and Trade – the contractor of the substation – had delayed the works since long putting forward various demands, which are not related with the contract. The contractor had asked NEA to remove the component of Inaruwa and Hetauda substations from the project or provide actual additional cost that accrue while implementing the project.
According to the contract between NEA and China Power Grid International Economic and Trade – in June 2014 – the substation was supposed to have been completed by September 2015. But the deadline was continuously pushed back as the contractor had sought additional incentives to complete the project on time.
Nepal plans to raise import of electricity via Muzaffarpur-Dhalkebar cross-border electricity transmission line. The country will be able to import an additional 100 megawatts (MW) of electricity on top of the existing 145 MW from India after the Dhalkebar substation – Rs 1.42 billion project under loan assistance of the World Bank – has been charged at 220 kV, which is critical to end load-shedding.
"The contractor has hardly worked for seven months though the construction work had started one-and-a-half years ago,” said project manager of Dhalkebar substation Radhesharan Mahato. "Some 85 per cent works of the project have been completed."
The NEA has already seized the bank guarantee of the contractor. However, the power utility has yet to select the next best option to expedite the project. After termination of the contract, NEA has a few options, like it can call for request for proposal (RfP) from the shortlisted companies, open a rebidding process or hand over a direct contract for remaining works to one of the earlier shortlisted companies.
Nepal-India energy secretary level talks held in February had also taken into account that the project will be completed by August this year.
The contractors normally generate profit from the delivery of equipment despite low bidding for the field level works and they seem reluctant to complete the project works on time. The NEA has also proposed to release 50 per cent of the payment for equipment only after the completion of works to make the contractor liable to complete the project works within the desired time.
Especially for projects funded by the World Bank, the executing agency has to release the payment for equipment to the contractor, after it submits the shipment order of the equipment.