The
Kathmanduites will have to wait again for two more years to drink water from
Melamchhi river as the much awaited water supply project is going to be delayed
from its original schedule to complete. The failure of contractor to complete
tunnel construction — the major component of the project — that will divert raw
water from Melamchi River to Sundarijal outlet in Kathmandu has also added cost
to the project that has become a ‘prestige project’ for the Asian Development
Bank (ADB).
However, ADB
– the key financier of the project – neither wants to abandon nor indulge into
any 'blame game for the failure' of earlier contractor to complete its task to
construct tunnel and move ahead with the Melamchhi Water Supply Project that
will pump 170 MLD water to the valley that has been waiting to quench its
thirst since 2002.
"The
ADB will neither blame anyone nor blacklist the contractor that has failed to
complete its task, rather will bring in more money, if necessary, to complete
the project," said director-general of ADB’s South Asia department Juan Miranda.
With ADB
pumping more money, the government might also have to jack up its matching fund
adding financial burden. "However, it is not finalised, yet,"
according to finance secretary Krishnahari Baskota.
"The
earlier price quoted by the contractor was not right," Miranda said,
adding that the project will select the new contractor — learning from past
experience — on the basis of quality and cost both, unlike earlier process that
was more concentrated on price only.
"We
have prepared the specific actions to move forward, including the smooth
settlement with the outgoing contractor, and swift selection of an
internationally reputed, committed and dedicated contractor, who can deliver
high quality infrastructure in a timely and efficient way," he added.
Melamchha
Water Supply Project witnessed a big setback last week after the contractor
'China Railway 15 Bureau Group Corporation' that was constructing the 22.5-km
long tunnel — the most expensive part — left only completing 6.5-km.
Chinese
contractor claimed that it was withdrawing from the contract due to financial
reason and lack of support from the board.
The project
has three parts; the tunnel, tripping plant, and the treatment and distribution
network in the Valley.
Originally
projected to cost $464 million in 2000, ADB had to restructure the project due
to withdrawal of other development partners in February 2008. After the
restructuring, the project has been revised to cost $317.3 million and the ADB
shouldered the largest financing share of $120 million.
"We
will not let the Kathmanduites down," Miranda said, adding that the
project will be completed by early 2016. "ADB is committed to alleviate
acute water supply shortages for the 2.6 million people in the Kathmandu
Valley."
However, the
project was initially projected to complete by 2013 and with the latest turn of
the events, Kathmanduites have to wait for two more years.
No comments:
Post a Comment